NHS 2027 carbon reduction plan requirements

In a competitive NHS tender, a bid can fail because its carbon reduction plan is missing a signature. Plans aren’t scored or compared. They pass or fail, and a plan with no signed declaration, no net zero commitment or no delivery measures is rejected.

From 1 April 2027, the bar rises. The 2027 NHS carbon reduction plan, required for larger contracts and new frameworks, asks suppliers to report all relevant Scope 3 emissions on a global boundary. This guide explains who it applies to, what the plan must contain, and how to build one, whether you’re a UK supplier or an overseas company bidding for NHS contracts directly or through a UK subsidiary.

What’s changing from 1 April 2027

The new requirements apply to procurements commenced from 1 April 2027. Procurements started before that date follow the existing rules. NHS England uses two tiers:

The 2027 NHS plan applies to contracts of £5 million a year or more (including VAT), and to all new frameworks, framework agreements and dynamic markets, unless the framework or market owner judges it disproportionate.

The 2024 plan continues for lower value contracts that sit above the relevant procurement thresholds. It aligns with the Cabinet Office’s PPN 006 plan.

Requirement2024 plan2027 NHS plan
Net zero commitmentBy 2050By 2050 or earlier (NHS recommends 2045)
Geographical boundaryUK as a minimumGlobal
Scope 3Five categoriesAll relevant categories
Target validation and offset disclosureNot requiredNot required, but recommended
Source: NHS England, 2027 NHS carbon reduction plan requirements.

Meeting the 2027 NHS plan also meets PPN 006, because it asks for more.

Does the 2027 NHS carbon reduction plan apply to you?

It depends on the type of procurement:

  • Contracts of £5m a year or more: the 2027 plan, assessed as a pass or fail requirement.
  • Frameworks: the 2027 plan is applied when the framework is tendered, not to individual call-offs. A framework owner can use the 2024 plan instead if it judges the 2027 plan disproportionate.
  • Dynamic markets: the 2027 plan is a condition of membership, and isn’t repeated when contracts are awarded under the market. The owner can use the 2024 plan instead if it judges the 2027 plan disproportionate.
  • Direct awards under the Procurement Act: the plan should be included in any selection criteria where possible. Where selection criteria aren’t used, suppliers are encouraged to submit a plan, but it isn’t assessed as pass or fail.
  • Health care services under the Provider Selection Regime: for direct award processes A and B, the plan is a due diligence question, not pass or fail. Under direct award process C, the most suitable provider process, the competitive process and framework agreements, the buyer assesses it as pass or fail.
  • Sub-contractors: not in scope, although suppliers should engage with them.

In exceptional circumstances, a buyer can decide not to apply the requirement at all where it isn’t proportionate, such as a distorted market, a civil emergency, or a light touch contract designed to help SMEs access public work where market engagement shows a plan would be a barrier.

NHS bodies bidding for contracts with other NHS organisations can submit their published Green Plan instead. Other public bodies need their own plan.

What you’ll be asked

Buyers use the same questions across regimes. You confirm that you’ve published a plan and give the link, confirm your commitment to net zero and your target date, and declare your baseline year and reporting year emissions for Scopes 1, 2 and 3.

How to build your 2027 NHS carbon reduction plan

1. Decide which entity reports

The plan can cover the supplier bidding for the NHS contract, or a parent can report on its behalf. A parent plan only counts if all of these are true: the supplier is wholly owned by the parent, the parent’s net zero commitment is expressly adopted by the supplier, with a statement in the plan that it applies to the supplier, the measures can be applied when delivering the contract, and the plan is published on the supplier’s website. Getting this wrong is itself a failure.

2. Set a global boundary

The boundary is global even if the bidder is a UK subsidiary. A UK subsidiary’s footprint includes related overseas emissions, such as overseas product purchasing and freight linked to UK activity. A multinational parent reporting on its behalf reports worldwide.

In our view, an overseas manufacturer is in scope when it’s the bidder, or the parent of the bidding subsidiary. One that only sells through a UK distributor isn’t directly in scope, because the requirement attaches to the supplier engaging with the NHS. But its products fall in the distributor’s own Scope 3 (purchased goods and services), so expect the distributor to ask it for emissions data.

3. Choose your baseline and reporting year

Pick a baseline year you can evidence and a current reporting year. As good practice, keep your boundary consistent between the two. The reporting period must fall no more than 18 months before the tender notice is published, unless you have an acceptable explanation.

4. Calculate your emissions, starting with Scopes 1 and 2

Report all scopes in tonnes of CO2e across the seven Kyoto gases: carbon dioxide, methane, nitrous oxide, hydrofluorocarbons, perfluorocarbons, sulphur hexafluoride and nitrogen trifluoride.

The UK government’s conversion factors for company reporting are designed for UK organisations and for international organisations reporting UK operations. The 2026 set, published in June, is for activity falling mostly within 2026, so match the factor year to your activity year. For activity outside the UK, use factors suited to that location. The UK set includes overseas electricity factors, but check coverage for other activities. One caution: the 2026 UK electricity factor uses a new method and is about 26% lower than 2025’s, so check before comparing years. Our guide to why the emission factor database matters more than the method explains why the factor behind each figure matters, and eco-shaper applies regionally specific emission factors.

5. Screen and estimate Scope 3

The 2027 plan covers all relevant Scope 3 categories under the GHG Protocol’s Scope 3 Standard, which defines 15. Screen each one. For any you judge not relevant, write down why, because an explanation is required.

Estimation is allowed, including spend-based methods. The UK government’s methodology paper for the 2026 factors separates the conversion factors from Defra’s spend-based multipliers, which it says can give an initial assessment of supply chain emissions based on spending. It asks users to report the methods they used. Spend-based is a sensible starting point but supplier-specific data is stronger for your largest categories. See when spend-based is enough and when it isn’t.

NHS England accepts that suppliers may not have full supply chain data. For NHS 2027/28 tenders, gaps in the additional Scope 3 data can pass with an acceptable explanation and a plan to report from the following year. This covers first-year gaps only, and buyers are told to write your reporting commitment into the contract. Any supplier with an acceptable reason for missing data, such as an SME or a voluntary, community or social enterprise, can also submit the emissions it has, with an explanation and steps to improve it. The buyer assesses this case by case.

6. Set your target and measures

Commit to net zero by 2050 or earlier (the NHS recommends 2045) for your whole organisation. As a minimum, the commitment applies to the supplier engaging with the NHS. Describe the environmental management measures you can deliver when performing the contract, such as certification schemes or specific carbon reduction measures. Third-party validation of targets and disclosure of how much you expect to rely on offsets are recommended, not required.

7. Approve, sign and publish

The plan needs board approval, or director approval if there’s no board, and a signed declaration. Publish it on your website with clear signposting, because buyers will ask for the link. NHS England asks for the structure and length of the PPN 006 template, with stylistic differences accepted. The template’s sections cover your net zero commitment, baseline and current emissions, targets, projects, and a declaration. Contract terms may require annual updates, and under the Provider Selection Regime, NHS bodies are expected to include that requirement.

NHS England’s worked examples of failing plans

  • No plan submitted, or no commitment to net zero
  • Emissions missing for some scopes without an explanation
  • A reporting period more than 18 months before the tender notice, without an explanation
  • No delivery measures for the contract
  • No signed declaration
  • A parent plan that doesn’t meet the conditions in step 1

What comes next

The NHS Net Zero Supplier Roadmap says that from 2030, suppliers will qualify for NHS contracts only if they can show progress through published reports and continued emissions reporting. The 2027 plan is a step on that path, so the supplier data you build now keeps its value.

Where eco-shaper can help

The hardest part of the plan is usually Scope 3. Supply chain engagement lets suppliers calculate their footprint once and share it with every customer who asks, so you receive supplier data without chasing spreadsheets. If you’re a supplier answering NHS requests, the Supplier Data System is built for that.

To talk through your own plan, book a call with our team.

NHS England, 2027 NHS carbon reduction plan requirements for the procurement of NHS goods, services and works, and the NHS Net Zero Supplier Roadmap.

Meeting the 2027 NHS plan also meets PPN 006, because it asks for more.

Does the 2027 plan apply to you?

It depends on the type of procurement:

  • Contracts of £5m a year or more: the 2027 plan, assessed as a pass or fail requirement.
  • Frameworks: the 2027 plan is applied when the framework is tendered, not to individual call-offs. A framework owner can use the 2024 plan instead if it judges the 2027 plan disproportionate.
  • Dynamic markets: the 2027 plan is a condition of membership, and isn’t repeated when contracts are awarded under the market. The owner can use the 2024 plan instead if it judges the 2027 plan disproportionate.
  • Direct awards under the Procurement Act: the plan should be included in any selection criteria where possible. Where selection criteria aren’t used, suppliers are encouraged to submit a plan, but it isn’t assessed as pass or fail.
  • Health care services under the Provider Selection Regime: for direct award processes A and B, the plan is a due diligence question, not pass or fail. Under direct award process C, the most suitable provider process, the competitive process and framework agreements, the buyer assesses it as pass or fail.
  • Sub-contractors: not in scope, although suppliers should engage with them.

In exceptional circumstances, a buyer can decide not to apply the requirement at all where it isn’t proportionate, such as a distorted market, a civil emergency, or a light touch contract designed to help SMEs access public work where market engagement shows a plan would be a barrier.

NHS bodies bidding for contracts with other NHS organisations can submit their published Green Plan instead. Other public bodies need their own plan.

What you’ll be asked

Buyers use the same questions across regimes. You confirm that you’ve published a plan and give the link, confirm your commitment to net zero and your target date, and declare your baseline year and reporting year emissions for Scopes 1, 2 and 3.

How to build your 2027 NHS carbon reduction plan

1. Decide which entity reports

The plan can cover the supplier bidding for the NHS contract, or a parent can report on its behalf. A parent plan only counts if all of these are true: the supplier is wholly owned by the parent, the parent’s net zero commitment is expressly adopted by the supplier, with a statement in the plan that it applies to the supplier, the measures can be applied when delivering the contract, and the plan is published on the supplier’s website. Getting this wrong is itself a failure.

2. Set a global boundary

The boundary is global even if the bidder is a UK subsidiary. A UK subsidiary’s footprint includes related overseas emissions, such as overseas product purchasing and freight linked to UK activity. A multinational parent reporting on its behalf reports worldwide.

In our view, an overseas manufacturer is in scope when it’s the bidder, or the parent of the bidding subsidiary. One that only sells through a UK distributor isn’t directly in scope, because the requirement attaches to the supplier engaging with the NHS. But its products fall in the distributor’s own Scope 3 (purchased goods and services), so expect the distributor to ask it for emissions data.

3. Choose your baseline and reporting year

Pick a baseline year you can evidence and a current reporting year. As good practice, keep your boundary consistent between the two. The reporting period must fall no more than 18 months before the tender notice is published, unless you have an acceptable explanation.

4. Calculate your emissions, starting with Scopes 1 and 2

Report all scopes in tonnes of CO2e across the seven Kyoto gases: carbon dioxide, methane, nitrous oxide, hydrofluorocarbons, perfluorocarbons, sulphur hexafluoride and nitrogen trifluoride.

The UK government’s conversion factors for company reporting are designed for UK organisations and for international organisations reporting UK operations. The 2026 set, published in June, is for activity falling mostly within 2026, so match the factor year to your activity year. For activity outside the UK, use factors suited to that location. The UK set includes overseas electricity factors, but check coverage for other activities. One caution: the 2026 UK electricity factor uses a new method and is about 26% lower than 2025’s, so check before comparing years. Our guide to why the emission factor database matters more than the method explains why the factor behind each figure matters, and eco-shaper applies regionally specific emission factors.

5. Screen and estimate Scope 3

The 2027 plan covers all relevant Scope 3 categories under the GHG Protocol’s Scope 3 Standard, which defines 15. Screen each one. For any you judge not relevant, write down why, because an explanation is required.

Estimation is allowed, including spend-based methods. The UK government’s methodology paper for the 2026 factors separates the conversion factors from Defra’s spend-based multipliers, which it says can give an initial assessment of supply chain emissions based on spending. It asks users to report the methods they used. Spend-based is a sensible starting point but supplier-specific data is stronger for your largest categories. See when spend-based is enough and when it isn’t.

NHS England accepts that suppliers may not have full supply chain data. For NHS 2027/28 tenders, gaps in the additional Scope 3 data can pass with an acceptable explanation and a plan to report from the following year. This covers first-year gaps only, and buyers are told to write your reporting commitment into the contract. Any supplier with an acceptable reason for missing data, such as an SME or a voluntary, community or social enterprise, can also submit the emissions it has, with an explanation and steps to improve it. The buyer assesses this case by case.

6. Set your target and measures

Commit to net zero by 2050 or earlier (the NHS recommends 2045) for your whole organisation. As a minimum, the commitment applies to the supplier engaging with the NHS. Describe the environmental management measures you can deliver when performing the contract, such as certification schemes or specific carbon reduction measures. Third-party validation of targets and disclosure of how much you expect to rely on offsets are recommended, not required.

7. Approve, sign and publish

The plan needs board approval, or director approval if there’s no board, and a signed declaration. Publish it on your website with clear signposting, because buyers will ask for the link. NHS England asks for the structure and length of the PPN 006 template, with stylistic differences accepted. The template’s sections cover your net zero commitment, baseline and current emissions, targets, projects, and a declaration. Contract terms may require annual updates, and under the Provider Selection Regime, NHS bodies are expected to include that requirement.

NHS England’s worked examples of failing plans

  • No plan submitted, or no commitment to net zero
  • Emissions missing for some scopes without an explanation
  • A reporting period more than 18 months before the tender notice, without an explanation
  • No delivery measures for the contract
  • No signed declaration
  • A parent plan that doesn’t meet the conditions in step 1

What comes next

The NHS Net Zero Supplier Roadmap says that from 2030, suppliers will qualify for NHS contracts only if they can show progress through published reports and continued emissions reporting. The 2027 plan is a step on that path, so the supplier data you build now keeps its value.

Where eco-shaper can help

The hardest part of the plan is usually Scope 3. Supply chain engagement lets suppliers calculate their footprint once and share it with every customer who asks, so you receive supplier data without chasing spreadsheets. If you’re a supplier answering NHS requests, the Supplier Data System is built for that.

To talk through your own plan, book a call with our team.

NHS England, 2027 NHS carbon reduction plan requirements for the procurement of NHS goods, services and works, and the NHS Net Zero Supplier Roadmap.

be an eco-shaper hero

Be a net-zero hero

At eco-shaper, we drive action on climate change and streamline carbon footprinting. For example, we can help calculate emissions across the entire ecosystem that companies work across and produce automated reporting based on outcomes. Contact us to be part of our research group on

Avatar photo
eco-shaper carbon reporting
United Kingdom

Registered Office:
86-90 Paul Street, London, EC2A 4NE
Registered in England No: 13717303

United States

Clarence Place, Unit 12
San Francisco
94107

Europe

Unit 1a, Block 1, Bracken Business Park
Sandyford, D18H283. Dublin, Ireland
Registered in Ireland No: 717904

Australasia

Hub Australia
223 Liverpool Street
Darlinghurst, NSW 2010